HydroTrace · Leak Detection · CCTV · GPR · Pipe Relining079 808 0531 | info@hydrotrace.co.za
Technical Case Study · Mpumalanga

Trenchless Pipe Rehabilitation Case Study in Highveld Park Apartment Block

Trenchless Pipe Rehabilitation technical case study in Highveld Park, Emalahleni: CCTV findings, PVC pipe, 160 mm diameter, epoxy brush coating and verification process.

Book Similar AssessmentView Trenchless Pipe Rehabilitation
LocationHighveld Park, Emalahleni
Pipe160 mm PVC
Length25 m assessed
Methodepoxy brush coating

Client Challenge

The body corporate trustees responsible for a multi-storey residential block in Highveld Park, Emalahleni needed a repair option that avoided unnecessary excavation. The reported issue was repeated blockages in the same section, with the main operational risk being damp walls, complaints from residents and costly access restrictions.

The affected route was located below a warehouse floor. That made open trench replacement more disruptive than a controlled diagnostic and trenchless rehabilitation approach.

CCTV Inspection Findings

HydroTrace would first verify the pipe internally before recommending relining. In this scenario, CCTV inspection indicated offset joints creating a ledge where solids and paper were catching. The host pipe was recorded as 160 mm PVC, with approximately 25 m requiring close assessment.

The inspection focus included pipe grade, deformation, connection points, water holding, silt deposits, joint condition and whether the host pipe was suitable for a liner or coating system.

Existing Pipe Details

  • Pipe material: PVC
  • Internal diameter: 160 mm
  • Assessed length: 25 m
  • Access restriction: below a warehouse floor
  • Failure mode: joint displacement

Recommended Rehabilitation Method

The selected approach was epoxy brush coating. This method involves cleaned pipe wall coated internally using a controlled brush-coating system. It was selected because it could reinstate the internal pipe surface while limiting demolition, downtime and reinstatement cost.

Preparation included de-scaling, jetting and measurement for a controlled liner installation. Preparation is critical because relining should never be installed over loose scale, grease, silt or unverified obstructions.

Installation Process

  1. Confirm access points and isolate the working section.
  2. Perform CCTV inspection and mark the affected distances.
  3. Clean the pipe using jetting, descaling or mechanical cleaning.
  4. Reinspect the pipe to confirm readiness for rehabilitation.
  5. Install the epoxy brush coating to the measured section.
  6. Allow the system to cure or set under controlled conditions.
  7. Carry out post-installation CCTV and flow verification.
  8. Issue a technical report with findings, photos or video references where available.

Project Outcome

The intended outcome was to restore flow, reduce water ingress, seal the damaged pipe wall and avoid unnecessary excavation around the multi-storey residential block. The estimated working window for this scenario was 1 day, depending on access, cleaning difficulty and curing requirements.

For similar sites in Highveld Park and Emalahleni, HydroTrace would recommend combining CCTV inspection, cleaning and post-repair verification so the client receives a defensible technical record instead of a guess-based repair.

Related HydroTrace Services

Trenchless Pipe Rehabilitation

Technical rehabilitation for damaged drainage, sewer, stormwater or pressure-related infrastructure.

Open service page

CCTV Pipe Inspection

Internal camera inspection to confirm pipe condition, defects, route and repair suitability.

View CCTV inspection

Leak Detection

Non-invasive investigation for hidden water loss, dampness and underground leaks.

View leak detection

FAQs

Why was pipe relining considered instead of excavation?

Relining was suitable because the damaged section was accessible from existing inspection points and excavation would have disrupted the site, finishes or operations.

Was CCTV inspection used before the relining decision?

Yes. CCTV inspection is used to confirm pipe condition, locate defects, measure distances and verify whether the line can be cleaned and rehabilitated internally.

Can this method work below concrete or paving?

Yes, where the host pipe still has enough structural profile and access is available, trenchless lining can rehabilitate sections below concrete, paving, roads or buildings.

Is pipe cleaning required before lining?

Yes. Jetting, descaling or mechanical cleaning is required so the liner or coating bonds against a prepared internal pipe surface.

What confirms that the repair worked?

Post-installation CCTV, flow verification and where applicable pressure or water testing are used to confirm the result.

Book an Inspection

Request a Booking

Complete the form and HydroTrace will confirm availability. For emergencies call 079 808 0531.

Preferred date & time *

Prefer to talk? Call 079 808 0531 or email info@hydrotrace.co.za